Decision 842/2022 Amending Award Authorization for Al-Hira Substation Renovation Contract

27-09-2022·مجلس الوزراء·الطاقة
Analysis
Summary

The Council of Ministers amended its earlier Decision 469/2022 to formally approve the award of a substation renovation contract to Al-Jeek Energy Company. The contract covers renovation and testing of the Al-Hira transformation station with a total value of LYD 2,787,848 (domestic component) plus EUR 1,275,288 (foreign component).

Business Implication

This decision confirms contract award to a specific energy contractor and demonstrates the GNU's continued investment in electricity infrastructure rehabilitation. For foreign energy contractors and equipment suppliers, it signals ongoing procurement activity in the power transmission sector, though this particular contract has been awarded. The amendment of the original decision suggests potential procedural corrections or commercial term adjustments that delayed finalization—a common procurement challenge in Libya's current operating environment.

Key Provisions
Contract awarded to Al-Jeek Energy Company for Al-Hira substation renovation and testing at 11/10/30/220 KV voltage levels
Total contract value: LYD 2,787,848 domestic component plus EUR 1,275,288 foreign component
All procedures must comply with Administrative Contracts Regulation provisions
Amendment replaces Article 1 of original Decision 469/2022
View original source ↗
Expert Commentary

No expert commentary yet on this document.

Ask about this document

Ask any question about this document — answered from the full Libyan regulatory corpus

Upgrade to use Q&A →